Storm Water Pollution Prevention Plan (SWPPP) Practice Test

Disable ads (and more) with a membership for a one time $2.99 payment

Prepare for the Storm Water Pollution Prevention Plan Test. Study using flashcards and multiple choice questions with hints and explanations. Ensure your success by acing your exam!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


Within how many days must active areas on a construction site be temporarily stabilized?

  1. 7 days

  2. 10 days

  3. 14 days

  4. 30 days

The correct answer is: 14 days

The requirement for temporary stabilization of active areas on a construction site is essential to prevent sediment and other pollutants from being washed into nearby water bodies. This is typically mandated to occur within a specific timeframe to ensure that exposed soil does not result in significant erosion. In this case, the correct answer specifies that active areas on a construction site must be temporarily stabilized within 14 days. This timeframe is based on guidelines set forth by regulatory agencies to mitigate impacts on water quality. Proper temporary stabilization techniques, such as erosion control blankets, seeded areas, or mulch, can significantly reduce sediment runoff and improve site conditions until permanent measures are implemented. Adhering to this 14-day requirement is crucial for compliance with the Storm Water Pollution Prevention Plan (SWPPP) and ultimately aids in protecting the environment during construction activities.